Project Commissioning Checklist
A Project Commissioning Checklist ensures that all systems, components, and equipment of a project are properly installed, tested, and fully operational. Using eAuditor Audits & Inspections to manage this process can help streamline and organize commissioning activities, ensuring that all tasks are properly documented and approved.
Below is a detailed Project Commissioning Checklist template that can be implemented in eAuditor Audits & Inspections.
Project Commissioning Checklist Template
General Information
- Project Name:
- Location:
- Client/Owner:
- Project Manager:
- Inspector Name:
- Commissioning Date:
- Commissioning Phase: (e.g., Pre-Commissioning, Functional Testing, System Handover)
1. Documentation Review
- Design Documents Approval: Verify the approval of all design documents and alignment with project specifications.
- Operation and Maintenance Manuals Available: Ensure O&M manuals are available for all equipment and systems.
- Inspection and Test Plans (ITP): Confirm the review of inspection and test plans are .
- Commissioning Plan Available: Verify the approval of commissioning plan and accessible.
- Verification of As-Built Drawings : Check that as-built drawings are accurate and reflect actual installations.
2. System Installation Verification
- System Installed as per Design: Ensure installation of all systems according to the design drawings and specifications.
- Equipment Installation Check: Confirm installation of all equipment (e.g., pumps, valves, control panels) in the correct location and orientation.
- Mechanical Components Inspected: Verify proper installation of mechanical components and are secure.
- Electrical System Installation: Confirm the proper installation of all electrical systems (wiring, panels, grounding, etc.).
- Safety Devices Installation: Ensure installation of safety devices (e.g., emergency stops, alarms) and make sure that they are functional.
- Labeling and Tagging: Verify that all systems and components are properly labeled and tagged.
3. Pre-Commissioning Checks
- Piping and Ductwork Inspection: Confirm that piping and ductwork are installed as per specifications, free of leaks, and properly insulated.
- Pressure Testing: Ensure all pressure tests are completed and results are documented.
- Electrical Continuity Testing: Verify electrical continuity and insulation resistance tests are completed.
- Rotation Check for Motors: Confirm that motor rotation has been checked and is correct.
- Calibration of Instruments: Ensure all sensors, gauges, and instruments are calibrated.
- Safety Devices Functional Test: Test all safety devices (e.g., relief valves, fire alarms, emergency shutdown systems).
- Control System Check: Verify that control systems (e.g., BMS, PLC) are functioning correctly.
4. Functional Testing
- Operational Readiness of Equipment: Check that all equipment operates per design specifications and under expected loads.
- Performance Testing of Systems: Conduct performance tests for major systems (e.g., HVAC, electrical distribution, fire suppression).
- Operational Tests with Controls: Test the system’s operational controls (e.g., start/stop sequences, interlocks, alarms).
- System Alarms and Faults: Verify that all system alarms and faults are functioning and recorded.
- Backup Power Testing: Test emergency generators or UPS systems for correct operation during power failure.
- System Response to Failures: Simulate failures (e.g., power outages, equipment shutdowns) and observe the system response.
5. Final System Integrity Checks
- Leaks and Defects Check: Ensure there are no leaks, vibrations, or other visible defects in the system.
- Electrical Grounding: Confirm Grounding of all equipment.
- Thermal Expansion: Verify the preparation of piping and mechanical systems for thermal expansion and contraction.
- Noise and Vibration Levels: Ensure that noise and vibration levels are within acceptable limits.
- Water Flow and Pressure: Confirm correct water flow and pressure in the system (if applicable).
- Cooling/Heating Systems Performance: Verify that heating, ventilation, and cooling systems operate as intended.
6. Health, Safety, and Environment (HSE)
- HSE Plan Followed: Confirm that the Health, Safety, and Environment (HSE) plan has been followed throughout the project.
- PPE Available and Used: Ensure that all workers have used the appropriate Personal Protective Equipment (PPE) during commissioning.
- Hazard Identification and Mitigation: Review any potential hazards identified during commissioning and ensure mitigation measures are in place.
- Work Area Clean and Safe: Verify that the work area is clean and free of obstructions or safety hazards.
- Emergency Procedures in Place: Ensure to communicate emergency procedures and available on-site.
7. Punch List and Deficiency Management
- Punch List Created: Develop a punch list of outstanding issues identified during commissioning.
- Deficiencies Corrected: Verify to address and correct all punch list items.
- Re-inspection of Corrected Items: Re-inspect corrected items to confirm they meet project specifications.
- Punch List Closed Out: Ensure to sign off and close all punch list items.
8. Documentation and Handover
- Commissioning Reports: Ensure to complete and document all commissioning test results and reports.
- O&M Manuals Delivery: Confirm the delivery of that operation and maintenance manuals to the client.
- As-Built Drawings Delivery: Verify the delivery of as-built drawings to the client.
- Training Completion: Ensure adequate training to the client and their team for operating and maintaining the systems.
- Client/Owner Approval: Obtain final sign-off from the client/owner representative for project handover.
9. Sign-Off and Approvals
- Inspector Signature:
- Client/Owner Representative Signature:
- Commissioning Engineer Signature:
- Date of Final Approval:
Using eAuditor Audits & Inspections for Project Commissioning Checklist
Steps to Implement:
- Create or use existing Project Commissioning Checklist Template in eAuditor Audits & Inspections:
- Input the Project Commissioning Checklist template into eAuditor Audits & Inspections using the template builder.
- Customize fields for specific project requirements (e.g., checkboxes, date/time fields, photo uploads, signatures).
- Assign Commissioning Tasks:
- Assign specific commissioning tasks or areas to the responsible personnel through eAuditor Audits & Inspections.
- Track Progress:
- Use eAuditor Audits & Inspection’s real-time dashboard to monitor the progress of commissioning activities. This allows managers to track completed tasks and identify outstanding issues.
- Capture Documentation:
- Utilize eAuditor Audits & Inspection’s photo capture feature to document installation, test results, and any deficiencies.
- Store all relevant documents such as test certificates, calibration results, and punch lists.
- Generate and Share Reports:
- Automatically generate detailed commissioning reports, including photos, notes, and signatures.
- Share reports in PDF format or through digital channels with stakeholders for review and approval.
- Monitor Compliance:
- eAuditor Audits & Inspection’s analytics can be used to monitor adherence to safety protocols, operational performance, and checklist completion.
Customization Tips for eAuditor Audits & Inspections for Project Commissioning Checklist
- Set up alerts for critical tasks (e.g., safety checks, leak testing).
- Integrate with project management tools to automate the flow of information between teams.
- Add form fields for equipment serial numbers, calibration records, and other details required for specific projects.
This checklist provides a comprehensive framework for ensuring the success of a project’s commissioning phase, while eAuditor Audits & Inspections makes the process more efficient, trackable, and documented.