Transformer Commissioning Checklist
Here’s a detailed Transformer Commissioning Checklist designed for use with eAuditor Audits & Inspections. This checklist covers all critical steps, from pre-installation to post-energization tests, ensuring proper and safe commissioning of a transformer.
Transformer Commissioning Checklist
1. General Information
- Project Name/Location:
- Transformer Manufacturer:
- Serial Number:
- Model Number:
- Voltage Rating:
- Power Rating:
- Type of Transformer: (e.g., Power, Distribution, Dry, Oil, etc.)
- Date of Commissioning:
- Commissioning Team:
- Client Representative:
2. Pre-Commissioning Preparation
- Documentation Check:
- Transformer manual and manufacturer’s instructions available.
- As-built drawings reviewed.
- Installation and test procedures outlined and agreed upon.
- Approved test plans available.
- Safety & Environment:
- Proper site access for equipment and personnel.
- Adequate grounding of transformer and associated equipment.
- Safety and warning signs posted.
- Ensure environmental protection measures (spill containment for oil, etc.).
- Equipment Inspection:
- Transformer visually inspected for physical damage.
- Confirm all components delivered are as per specification (e.g., bushings, tap changers, radiators, fans).
- Verify nameplate information matches the purchase order.
3. Transformer Installation Checks
- Positioning & Foundation:
- Ensure transformer is positioned according to the design layout.
- Verify correct alignment and leveling.
- Ensure proper vibration damping measures are in place.
- Grounding:
- Verify the transformer is adequately grounded.
- Confirm that neutral grounding is installed as per the design.
- Test the continuity of grounding connections.
- Terminations & Connections:
- Verify that high-voltage (HV) and low-voltage (LV) cables are correctly terminated.
- Check that all connections (HV, LV, neutral, ground) are secure and in accordance with drawings.
- Verify the correct polarity and phasing of connections.
- Cooling System:
- Confirm that cooling fans, radiators, and oil pumps (if applicable) are properly installed and secured.
- Ensure proper connections for cooling system electrical and control circuits.
4. Oil-Filled Transformer Specific Checks (if applicable)
- Oil Levels and Quality:
- Verify correct oil level in the conservator tank.
- Perform oil sampling and testing (dielectric strength, moisture content, DGA – dissolved gas analysis).
- Confirm oil is free of contaminants.
- Breather System:
- Ensure silica gel in the breather is fresh and functioning.
- Check the correct connection of the breather to the conservator tank.
- Pressure Relief Devices:
- Verify pressure relief device is correctly installed and functional.
- Test alarm/trip signals connected to the pressure relief system.
5. Pre-Energization Electrical Testing
- Insulation Resistance Testing (Megger Test):
- Test insulation resistance between winding phases, between windings, and between winding and ground.
- Record results for comparison against manufacturer’s standards.
- Transformer Turns Ratio (TTR) Test:
- Perform TTR test to verify proper winding ratios.
- Confirm results are within acceptable limits.
- Winding Resistance Test:
- Measure and record winding resistances of all windings.
- Ensure resistances match design specifications.
- SFRA (Sweep Frequency Response Analysis):
- Conduct SFRA test to assess the mechanical integrity of the transformer core and windings.
- Power Factor/Dissipation Factor Testing (Tan Delta):
- Test insulation power factor for all windings to assess insulation condition.
- Polarity and Phase Verification:
- Verify correct polarity of windings.
- Perform phase verification test to confirm correct phase connections.
6. Protection and Control Systems
- Relays & Protection Settings:
- Verify the protection relays (overcurrent, differential, etc.) are correctly installed and settings are as per design.
- Test the functionality of all relays by simulating faults.
- Buchholz Relay (for Oil-Filled Transformers):
- Verify Buchholz relay functionality.
- Test for proper connection to the alarm/trip circuit.
- On-Load Tap Changer (OLTC):
- Confirm correct operation of the OLTC.
- Check OLTC control panel and ensure proper communication with SCADA/DCS.
- Perform OLTC step change test.
- Cooling System Operation:
- Test the operation of cooling fans and oil pumps under normal and emergency conditions.
- Verify temperature monitoring and control circuits (RTDs, thermocouples, etc.).
7. Grounding System Tests
- Ground Resistance Test:
- Perform ground resistance testing of the transformer’s grounding system.
- Ensure resistance is within acceptable limits.
- Continuity Test:
- Perform continuity tests on all grounding connections.
- Verify all metal parts (tank, radiators, etc.) are properly bonded.
8. Final Pre-Energization Checks
- Physical Inspection:
- Conduct a final inspection to ensure no tools or foreign materials are left in or around the transformer.
- Ensure all covers and access points are securely closed.
- Communication Systems:
- Confirm communication between transformer and control system (SCADA, RTUs).
- Verify proper signal transmission for alarms, status indications, and measurements.
- Final Review of Test Results:
- Review and confirm all pre-energization test results are within acceptable ranges.
9. Energization Procedure
- Approval to Energize:
- Obtain formal approval from relevant stakeholders to energize.
- Ensure all personnel are cleared from the vicinity.
- Initial Energization:
- Apply voltage gradually (if applicable).
- Monitor for unusual noises, vibrations, or other abnormal conditions.
- Ensure cooling system operates as expected under load.
10. Post-Energization Checks
- Voltage and Load Readings:
- Record voltage levels on HV and LV sides.
- Monitor the transformer under load for 24–48 hours.
- Temperature Monitoring:
- Monitor oil and winding temperatures.
- Ensure the cooling system adjusts according to the load and temperature rise.
- Buchholz Relay and Protection Alarms:
- Monitor for any abnormal alarms during initial operation.
- Confirm protection relays are functioning as designed.
11. Completion and Sign-Off
- Commissioning Completed By:
- Name/Signature:
- Date:
- Reviewed and Approved By:
- Name/Signature:
- Date:
- Client Representative:
- Name/Signature:
- Date:
How to Use Transformer Commissioning Checklist in eAuditor Audits & Inspections
- Create a Template: In eAuditor Audits & Inspections, create a new template using Transformer Commissioning Checklist structure provided above or use existing Transformer Commissioning Checklist from eAuditor.
- Customize Fields: Modify the checklist to suit the specific transformer type, equipment, and site conditions. You can add or remove fields as needed.
- Use Checkboxes & Input Fields: Include checkboxes for each item, and input fields for test results, inspector comments, and signatures.
- Add Photos: Take photos during inspections and tests and attach them directly to the checklist.
- Generate Reports: After completing the checklist, use eAuditor Audits & Inspection’s reporting feature to generate PDF reports and share them with the team and client.
This checklist ensures that all necessary steps in the commissioning of a transformer are covered, promoting safe and effective operation from the start.