Substation Commissioning Checklist
Using eAuditor Audits & Inspections  for substation commissioning is a great way to streamline inspections, ensure thoroughness, and maintain documentation. Below is a general substation commissioning checklist that can be used with eAuditor Audits & Inspections. It includes a wide range of items typically checked during the commissioning process.
Substation Commissioning Checklist
1. General Information
- Site Name/Location:
- Commissioning Date:
- Commissioning Engineer(s):
- Weather Conditions:
- Substation Voltage Level:
- Type of Substation: (AIS/GIS)
- Main Contractor:
- Subcontractor(s):
2. Pre-Commissioning Checks
- Site Access:
- Ensure clear access to the site for equipment and personnel.
- Verify access control and safety measures in place.
- Documentation:
- Verify as-built drawings are complete and available.
- Equipment manuals and manufacturer instructions on site.
- Safety documentation and risk assessments reviewed.
- Environmental Checks:
- Ensure proper grounding of all substation equipment.
- Check the drainage system and flood prevention measures.
- Check for environmental protections (oil containment, chemical handling).
3. Health, Safety, and Security
- PPE available and in use (hard hats, gloves, safety glasses, etc.).
- Verify all personnel are trained in emergency protocols.
- First-aid kits and emergency contact numbers on site.
- Fire extinguishers are accessible and functional.
- Warning signage properly posted (high-voltage, arc flash, etc.).
- Security systems (CCTV, fencing) operational.
4. Transformer Testing
- Transformer Type: (Oil/ Dry-type / Gas-insulated)
- Pre-Energization Testing:
- Insulation resistance (megger test).
- Transformer turns ratio (TTR) test.
- Sweep frequency response analysis (SFRA).
- Oil sampling and testing (if applicable).
- Power factor/dissipation factor test.
- Neutral grounding resistances tested.
- Protection Systems:
- Check Buchholz relay function.
- Confirm OLTC (on-load tap changer) operation and control.
- Verify protection relay settings as per the design.
- Test the functionality of cooling systems (fans, pumps, oil circulation).
5. Circuit Breakers
- Pre-Energization Testing:
- Insulation resistance test.
- Circuit breaker timing test.
- Contact resistance measurement.
- Functional operation test (open/close command).
- Check SF6 pressure level (for gas-insulated breakers).
- Gas leak detection (if applicable).
- Verify auxiliary contacts.
- Operational Checks:
- Trip and close mechanism functional.
- Spring charging motor and hydraulic system operational.
- Confirm correct relay tripping action.
6. Switchgear
- Visual inspection for damage or defects.
- Insulation resistance tests.
- Circuit isolation tested.
- Operational testing (manual and remote controls).
- Earthing system verification.
- Phase verification (polarity checks).
- Confirm interlocking system works as designed.
7. Protection Systems
- Protection Relay Testing:
- Overcurrent relay tested.
- Differential relay tested.
- Distance protection tested.
- Backup protection functional.
- Verify relay communication to SCADA/DCS systems.
- Alarm Systems:
- Audible and visual alarms tested.
- SCADA alarm verification.
- Backup power supplies tested for alarms.
8. Control and Instrumentation
- Verify SCADA/DCS connectivity.
- Confirm all communication cables are properly terminated.
- Ensure correct time synchronization between substation devices.
- Voltage, current, and power metering accuracy.
- Verify CTs (current transformers) and PTs (potential transformers) are correctly installed and connected.
- Signal checks from field devices (voltage/current transducers, temperature sensors, etc.).
9. Grounding System
- Visual inspection of grounding system.
- Grounding system resistance test (earth resistance).
- Verify connection to ground grid.
- Confirm grounding connections to all equipment.
- Test continuity of grounding system.
10. Battery and Auxiliary Power Systems
- Battery bank installation inspection.
- Verify automatic changeover to backup power.
- Battery voltage and current measurement.
- Battery load test.
- Test charger function and alarms.
11. Busbar and Insulators
- Insulation resistance test of busbars.
- Visual inspection of busbars and insulators.
- Confirm correct phase identification and connections.
- Check for proper clearance from other equipment.
12. Cables and Wiring
- Cable Testing:
- Cable megger testing.
- High-potential (Hi-Pot) test.
- Cable sheath testing.
- Cable Installation:
- Verify correct routing and labeling.
- Terminations and joints properly executed.
- Adequate cable supports and fixings installed.
13. Lightning Arresters
- Visual inspection of lightning arresters.
- Verify the installation and grounding.
- Measure insulation resistance of the lightning arresters.
14. Final Energization Checks
- Confirm final relay settings.
- Pre-energization checks completed and signed off.
- Final review of all test results.
- Approval from all stakeholders for energization.
15. Post-Energization Tests
- Voltage and load checks under operational conditions.
- Monitor for unusual noises, overheating, or abnormal behavior.
- Test automatic voltage regulation system.
- Monitoring of equipment behavior for the first 24 hours post-energization.
16. Sign-Off
- Inspection Completed By:
- Name/Signature:
- Date:
- Reviewed By (Supervisor):
- Name/Signature:
- Date:
- Client Representative Approval:
- Name/Signature:
- Date:
How to Use Substation Commissioning Checklist in eAuditor Audits & Inspections:
- Create or use existing Substation Commissioning Checklist: Create a new template in eAuditor Audits & Inspections and use existing Substation Commissioning Checklist or build the checklist.
- Customize Fields: Adjust any fields to meet the specific requirements of the substation project, adding or removing tests based on equipment.
- Set up Automation: Use eAuditor Audits & Inspection’s automation tools to set reminders for key inspections or follow-ups during and after the commissioning.
- Add Photos & Comments: Use eAuditor Audits & Inspection’s feature to attach images, comments, and evidence of inspections for each section.
- Generate Reports: After completing the checklist, generate and share reports instantly with the team.
By utilizing eAuditor Audits & Inspections for substation commissioning, you can ensure that all key tasks are performed, documented, and communicated efficiently.